Current project information.

The project is approximately 23% complete.

 

Miller Road Detour to Be Lifted Friday 12/12

We’re pleased to share that the Miller Road west leg detour at Randall Road will be lifted on Friday, December 12. Once lifted, traffic will flow freely through the intersection, restoring complete access to Miller Road. Thank you for your continued patience throughout this phase of the Randall Road Improvements[...]

READ MORE

Randall Road Project Update

The week of 12/08/2025, scheduled work includes: Miller Road Bridge: Continue pavement work adjacent to the bridge Ground Improvements: Continue installation of pile caps and load transfer platform Woods Creek Bridge: Installation of rebar, forming, and pouring piers Roadway Work: Miller Road backfill of newly poured curb Miller Road and[...]

READ MORE